II. International Competitive Bidding - C. Bid Opening, Evaluation and Award of Contract
Time for Preparation of Bids
2.43 ... The time allowed for the preparation and submission of bids shall be determined with due consideration of the particular circumstances of the project and the magnitude and complexity of the contract. Generally, not less than six weeks from the date of the invitation to bid or the date of availability of bidding documents, whichever is later, shall be allowed for ICB. Where large works or complex items of equipment are involved, this period shall generally be not less than twelve weeks to enable prospective bidders to conduct investigations before submitting their bids. In such cases, the Borrower is encouraged to convene pre-bid conferences and arrange site visits. Bidders shall be permitted to submit bids by mail or by hand. The deadline and place for receipt of bids shall be specified in the invitation to bid.
Bid Opening Procedures
2.44 ... The time for the bid opening shall be the same as for the deadline for receipt of bids or promptly 31 thereafter, and shall be announced, together with the place for bid opening, in the invitation to bid. The Borrower shall open all bids at the stipulated time and place. Bids shall be opened in public; that is, bidders or their representatives shall be allowed to be present. The name of the bidder and total amount of each bid, and of any alternative bids if they have been requested or permitted, shall be read aloud and recorded when opened and a copy of this record shall be promptly sent to the Bank. Bids received after the time stipulated, as well as those not opened and read out at bid opening, shall not be considered.
Clarifications or Alterations of Bids
2.45 ... Except as otherwise provided in paragraphs 2.61 and 2.62 of these Guidelines, bidders shall not be requested or permitted to alter their bids after the deadline for receipt of bids. The Borrower shall ask bidders for clarification needed to evaluate their bids but shall not ask or permit bidders to change the substance or price of their bids after the bid opening. Requests for clarification and the bidders' responses shall be made in writing.
Confidentiality
2.46 ... After the public opening of bids, information relating to the examination, clarification and evaluation of bids and recommendations concerning awards shall not be disclosed to bidders or other persons not officially concerned with this process until the award of contract is notified to the successful bidder.
Examination of Bids
2.47 ... The Borrower shall ascertain whether the bids (i) meet the eligibility requirements specified in paragraph 1.6 of these Guidelines, (ii) have been properly signed, (iii) are accompanied by the required securities, (iv) are substantially responsive to the bidding documents, and (v) are otherwise generally in order. If a bid is not substantially responsive, that is, it contains material deviations from or reservations to the terms, conditions and specifications in the bidding documents, it shall not be considered further. The bidder shall not be permitted to correct or withdraw material deviations or reservations once bids have been opened. 32
Evaluation and Comparison of Bids
2.48 ... The purpose of bid evaluation is to determine the cost to the Borrower of each bid in a manner that permits a comparison on the basis of their evaluated cost 33. Subject to paragraph 2.57, the bid with the lowest evaluated cost, but not necessarily the lowest submitted price, shall be selected for award.
2.49 ... The bid price read out at the bid opening shall be adjusted to correct any arithmetical errors. Also, for the purpose of evaluation, adjustments shall be made for any quantifiable nonmaterial deviations or reservations. Price adjustment provisions applying to the period of implementation of the contract shall not be taken into account in the evaluation.
2.50 ... The evaluation and comparison of bids shall be on CIF or CIP prices for the supply of imported goods and EXW prices for goods offered from within the Borrower's country, together with prices for any required installation, training, commissioning and other similar services.
2.51 ... Bidding documents shall also specify the relevant factors in addition to price to be considered in bid evaluation and the manner in which they will be applied for the purpose of determining the lowest evaluated bid. For goods and equipment, other factors which may be taken into consideration include, among others, costs of inland transport and insurance to the specified site, payment schedule, delivery time, operating costs, efficiency and compatibility of the equipment, availability of service and spare parts, and related training, safety and environmental benefits. The factors other than price to be used for determining the lowest evaluated bid shall, to the extent practicable, be expressed in monetary terms, or given a relative weight in the evaluation provisions in the bidding documents.
2.52 ... Under works and turnkey contracts, contractors are responsible for all duties, taxes and other levies 34, and bidders shall take these factors into account in preparing their bids. The evaluation and comparison of bids shall be on this basis. Bid evaluation for works shall be strictly in monetary terms. Any procedure under which bids above or below a predetermined assessment of bid values are automatically disqualified is not acceptable. If time is a critical factor, the value of early completion to the Borrower may be taken into account according to criteria presented in the bidding documents, only if the conditions of contract provide for commensurate penalties for noncompliance.
2.53 ... The Borrower shall prepare a detailed report on the evaluation and comparison of bids setting forth the specific reasons on which the recommendation is based for the award of the contract.
Domestic Preferences
2.54 ... At the request of the Borrower, and under conditions to be agreed under the Loan Agreement and set forth in the bidding documents, a margin of preference may be provided in the evaluation of bids for:
(a) goods manufactured in the country of the Borrower when comparing bids offering such goods with those offering goods manufactured abroad; and (b) works in member countries below a specified threshold of GNP 35 per capita, when comparing bids from eligible domestic contractors with those from foreign firms.
2.55 ... Where preference for domestically manufactured goods or for domestic contractors is allowed, the methods and stages set forth in Appendix 2 to these Guidelines shall be followed in the evaluation and comparison of bids.
Extension of Validity of Bids
2.56 ... Borrowers shall complete evaluation of bids and award of contract within the initial period of bid validity so that extensions are not necessary. An extension of bid validity, if justified by exceptional circumstances, shall be requested in writing from all bidders before the expiration date. The extension shall be for the minimum period required to complete the evaluation, obtain the necessary approvals and award the contract. In the case of fixed price contracts, requests for second and subsequent extensions will be permissible only if the request for extension provides for an appropriate adjustment mechanism of the quoted price to reflect changes in the cost of inputs for the contract over the period of extension. Whenever an extension of bid validity period is requested, bidders shall not be requested or be permitted to change the quoted (base) price or other conditions of their bid. Bidders shall have the right to refuse to grant such an extension without forfeiting their bid security, but those who are willing to extend the validity of their bid shall be required to provide a suitable extension of bid security.
Postqualification of Bidders
2.57 ... If bidders have not been prequalified, the Borrower shall determine whether the bidder whose bid has been determined to offer the lowest evaluated cost has the capability and resources to effectively carry out the contract as offered in the bid. The criteria to be met shall be set out in the bidding documents, and if the bidder does not meet them, the bid shall be rejected. In such an event, the Borrower shall make a similar determination for the next lowest evaluated bidder.
Award of Contract
2.58 ... The Borrower shall award the contract, within the period of the validity of bids, to the bidder who meets the appropriate standards of capability and resources and whose bid has been determined (i) to be substantially responsive to the bidding documents and (ii) to offer the lowest evaluated cost 36. A bidder shall not be required, as a condition of award, to undertake responsibilities for work not stipulated in the bidding documents or otherwise to modify the bid as originally submitted.
Rejection of All Bids
2.59 ... Bidding documents usually provide that Borrowers may reject all bids. Rejection of all bids is justified when there is lack of effective competition, or bids are not substantially responsive. However, lack of competition shall not be determined solely on the basis of the number of bidders. If all bids are rejected, the Borrower shall review the causes justifying the rejection and consider making revisions to the conditions of contract, design and specifications, scope of the contract, or a combination of these, before inviting new bids.
2.60 ... If the rejection of all bids is due to lack of competition, wider advertising shall be considered. If the rejection is due to most or all of the bids being nonresponsive, new bids may be invited from the initially prequalified firms, or with the agreement of the Bank from only those that submitted bids in the first instance.
2.61 ... All bids shall not be rejected and new bids invited on the same bidding and contract documents solely for the purpose of obtaining lower prices. If the lowest evaluated responsive bid exceeds the Borrower's pre-bid cost estimates by a substantial margin, the Borrower shall investigate causes for the excessive cost and consider requesting new bids as described in the previous paragraphs. Alternatively, the Borrower may negotiate with the lowest evaluated bidder to try to obtain a satisfactory contract through a reduction in the scope and/or a reallocation of risk and responsibility which can be reflected in a reduction of the contract price. However, substantial reduction in the scope or modification to the contract documents may require rebidding.
2.62 ... The Bank's prior concurrence shall be obtained before rejecting all bids, soliciting new bids or entering into negotiations with the lowest evaluated bidder.
(next section: Modified ICB)
_______________________
Footnotes
(31). To allow sufficient time to take the bids to the place announced for public bid opening.
(32). See para. 2.49 regarding corrections.
(33). See para. 2.51.
(34). Unless bidding documents specify otherwise for some turnkey contracts (see para. 2.22 and footnote 25).
(35). Gross national product as defined annually by the Bank.
(36). Referred to as "lowest evaluated bidder" and "lowest evaluated bid," respectively.