Table 4

Unit Costs of Road Works as contained in the
Latvian Road Administration Progress Report for June 1999

Pavements

Unit

US$1
Pothole patching-t70.31
Pothole patching-m28.50
Pothole patching-m9.08
Crack sealing with bitumen-m21.22
Crack sealing with bitumen-m1.03
Tack coating-m20.31
Milling of asphalt concrete joints-m23.58
Milling of asphalt concrete pavement-m22.31
Cold recycling 6 cmm22.75
Depression filling-t39.42
Asphalt concrete leveling course construction-t45.34

.

3 cmm23.17

.

4 cmm24.22
-6 cmm26.59

-

7 cmm27.71
Asphalt wearing course construction-t50.05

-

3 cmm23.66

-

3.5 cmm24.27

-

4 cmm24.86

-

5 cmm26.07

-

6 cmm27.31
Asphalt concrete bottom course construction-t48.12

-

5 cmm25.59

-

6 cmm26.71
Remix Plus technology (milling+hot mix)-m25.15
Single surface dressing-m21.58
Double surface dressing-m22.66
1Exchange rate used: US$1=0.59 LVL