Item
|
Unit
|
US$1
|
 |
Ready-mixed concrete
(strength) 16 - 40 N/mm2
(slump) 8 - 21 cm
(aggregate) 25 mm |
m3 |
$112.0 - $149.5 |
Tokyo, carried in the site, assumed volume:
1000 - 2000 m3 |
| Normal Portland Cement |
t |
$89 |
Tokyo, carried in the site, assumed volume:
300 - 1000 tons |
Steel Plate (size)
- 6@914@1829mm to
- 25@1524@6096mm
|
t |
$400 - $450 |
Tokyo, carried in the site, assumed volume:
20 - 30 tons |
Asphalt Mixture
(aggregate factor 13 to 20) |
t |
$67 - $87 |
Tokyo, carried in the site,
assumed volume:
200 - 2000 tons |
|
Cut-back Asphalt for surface treatment
|
t |
$940 |
Kanto (region of Tokyo), carried in the site, assumed volume:
10 tons |
| 1Exchange rate used: US$1 = 100 JPY |
| Source: Kensetsu Bukka, February 2000, by the Kensetsu Bukka Chousakai foundation |