The Eastern Electricity Highway Project under the First Phase of the Eastern Africa Power Integration Program

Africa

OverviewFinancialProcurementImplementation & ResultsNews & Related Info
 
Project ID: P126579 | Project Status: Active

 

Abstract* last updated 25-JUN-2012
 
The development objective of the Regional Eastern Africa Power Pool Project First Adaptable Program Loan (APL1) for Africa is to increase the volume and reduce the cost of electricity supply in Kenya; and to provide revenues to Ethiopia through the export of electricity from Ethiopia to Kenya. There are two components to the project. The first component is construction of a High Voltage Direct Current (HVDC) transmission interconnection between Ethiopia and Kenya. This component includes four su...More»
 
Expand / Collapse Keywords SectionKeywords

Project-At-A-Glance
Approval Date12-JUL-2012
Closing Date30-JUN-2019
Total Project Cost**1262.5
RegionAfrica
Major Sector (Sector) (%)Energy and mining (General energy sector) (100%)
Themes (%)Regional integration (90%)
 Infrastructure services for private sector development (10%)
Environmental CategoryA
Bank Team LeadKoljonen, Paivi
Borrower/RecipientGOVERNMENTS OF ETHIOPIA AND KENYA
Implementing AgencyGOVERNMENTS OF EHTIOPIA AND KENYA
Project Goals
To view the project outcomes and goals click  here.

Available Project Documents
Implementation Status and Results Report (ISRR), Vol.22-FEB-2013
Procurement Plan (PROP), Vol.1 of 114-AUG-2012
Summary of Discussion (Summary of Discussion), Vol.1 of 112-JUL-2012
More»

Related Country Information
To view information on the country where the project is implemented click  here.

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature.
**Total project cost includes funding from World Bank and non-bank sources in US$ millions. Active and Closed projects show commitment at Board approval. It does not reflect any cancellations. Proposed (pipeline) and dropped projects show the forecast amount. The commitment amount for projects in the pipeline is indicative and may be modified during the project preparation.

Projects Home | Advanced Projects Search | Contract/Contractors Search | Browse | Help/FAQ